Risk assessment of the causes of cost overrun of project XYZ

Authors

  • Suci Ramadhani Institut Pertanian Bogor
  • Widodo Ramadyanto Institut Pertanian Bogor
  • Siti Jahroh Institut Pertanian Bogor

DOI:

https://doi.org/10.55324/ijoms.v3i11.971

Keywords:

risk assessment, cost overrun, construction

Abstract

Cost overrun is a phenomenon that often occurs in the construction of a construction project. The purpose of this study is to analyze the main factors causing cost overrun in project XYZ based on the results of sensitivity analysis to the variables that form RAP. The results show that the cost element of subcontractors has a very large effect on the total RAP of the subcontractor, and the most dominant work affecting is steel work and panel sandwich work. The RAP weight of the work that affects the RAP is between 22.84% and 43.39%, followed by panel sandwich works and bridge steel work. It is recommended that PT X evaluate the performance of each related bureau, especially the estimating and engineering bureaus, in calculating RAP analysis and considering potential long-term risks.

References

Anwar, N. (2013). KAPAN INVESTASI MEMPUNYAI DAMPAK TERHADAP EKONOMI? Proceeding of International Conference Sustainable Competitive Advantage.

Bear, L. (2020). Speculations on infrastructure: from colonial public works to a post-colonial global asset class on the Indian railways 1840–2017. Economy and Society, 49(1). https://doi.org/10.1080/03085147.2020.1702416

Bentil, E., Addy, R. E. N., Asare, E. K., & Kuci, A. F. (2017). The level of existence and impact of cost and time overruns of building construction projects in Ghana. Civil and Environmental Research, 9(1).

Darmanto, B., Widjayakusuma, J., & Simanjuntak, M. R. A. (2020). Identifikasi Faktor-Faktor yang Menyebabkan Cost Overrun pada Konstruksi Gedung Bertingkat. Prosiding Seminar Nasional Teknik Sipil 2020 Fakultas Teknik Universitas Muhammadiyah Surakarta.

Fadjar, A. (2008). Aplikasi Simulasi Monte Carlo Dalam Estimasi Biaya Proyek. Jurnal SMARTek, 6(4).

Hadinata, G. W., Nadiasa, M., & Widhiawati, I. A. R. (2013). Analisis faktor-faktor penyebab pembengkakan realisasi biaya terhadap rencana anggaran pelaksanaan pada proyek konstruksi gedung. Jurnal Ilmiah Elektronik Infrastruktur Teknik Sipil, 2(2).

Ho, S. (2020). Infrastructure and Chinese power. International Affairs, 96(6). https://doi.org/10.1093/ia/iiaa171

Maddeppungeng, A., Bethary, R. T., & Wibowo, D. H. (2013). STUDI PENGARUH KETERLAMBATAN PROYEK TERHADAP COST OVERRUNS PROYEK. Fondasi?: Jurnal Teknik Sipil, 2(2). https://doi.org/10.36055/jft.v2i2.1729

Nega, F. (2008). Causes and effects of cost overrun on public building construction projects in Ethiopia [Master Thesis]. Addis Ababa University.

Puteri, L. A. L., Dhiu, C. H., Syharto, M. E., & Purba, H. H. (2022). Analisis Risiko Cost Overrun (Pembengkakan Biaya) Pada Proyek Konstruksi: Kajian Literatur. Jurnal Rekayasa Sipil Dan Lingkungan, 5(2). https://doi.org/10.19184/jrsl.v5i2.27915

Rani, H. A. (2016). Manajemen Proyek Konstruksi. Deepublish.

Remi, F. F. (2017). KAJIAN FAKTOR PENYEBAB COST OVERRUN PADA PROYEK KONSTRUKSI GEDUNG. Jurnal Teknik Mesin, 6(2). https://doi.org/10.22441/jtm.v6i2.1187

Sahusilawane, T., Bisri, M., Rachmansyah, A., Negeri Ambon, P., & Pengairan, J. T. (2011). Analisis Faktor-Faktor Penyebab Terjadinya Pembengkakan Biaya (Cost Overrun) pada Proyek Konstruksi Gedung di Kota Ambon. Rekayasa Sipil, 5(2).

Sajiah, F. S. (2022). Keterkaitan antar Faktor Penyebab Pembengkakan Biaya pada Proyek Transportasi dengan Kontrak Tahun Jamak. JURNAL MANAJEMEN KEUANGAN PUBLIK, 6(2). https://doi.org/10.31092/jmkp.v6i2.1419

Stone, F., Hutagalung, D. O. S., Hermawan, F., & Khasani, R. R. (2017). Pengaruh Pola Kebijakan Produktifitas Konstruksi Indonesia Terhadap Daya Saing Infrastruktur. Jurnal Karya Teknik Sipil, 6(4).

Downloads

Published

2024-08-31